MARITIME TERMINAL OF
COMPLEX
  Technical Specification of Gangway
(CHEC NO: 13303)
                  (CLIENT NO: 013)
China Engineering Co. Ltd. (C)
September, 2015
Issue status:
register for
0C
Sep. 2015
2014
FOR APPROVAL
Rev.
Date
Description
Prep’d
Chk’d
Rev’d
App’d
CONTENTS
1    GENERAL    错误!未定义书签。
1.1    FIELD OF APPLICATION    错误!未定义书签。
1.2    DEFINITION OF ITEMS    错误!未定义书签。
2    REFERENCE DOCUMENTS    错误!未定义书签。
2.1    APPLICABLE CODES AND STANDARDS    错误!未定义书签。
2.2    APPLICABLE PROJECT DOCUMENTS    错误!未定义书签。
2.3    EXCEPTIONS TO REFERENCE DOCUMENTS    错误!未定义书签。
2.4    DOCUMENTS ORDER OF PRECEDENCE    错误!未定义书签。
3    SCOPE OF SUPPLY    错误!未定义书签。
3.1    EQUIPMENT SUPPLY    错误!未定义书签。
3.2    EXCLUSIONS    错误!未定义书签。
3.3    BOUNDARY LIMITS    错误!未定义书签。
3.4    ERECTION WORKS    错误!未定义书签。
4    INSTALLATION DATA    错误!未定义书签。
4.1    SITE LOCATION AND ENVIRONMENTAL CONDITIONS    错误!未定义书签。
4.2    AREA CLASSIFICATION    错误!未定义书签。
5    GENERAL SERVICE CONDITIONS    错误!未定义书签。
5.1    PROCESS    错误!未定义书签。
5.2    OPERATING AND DESIGN CONDITIONS    错误!未定义书签。
6    DESIGN AND CONSTRUCTION    错误!未定义书签。
6.1    MATERIALS    错误!未定义书签。
6.2    DESIGN REQUIREMENTS    错误!未定义书签。
6.3    SWIVEL JOINTS AND STRUCTURAL BEARINGS    错误!未定义书签。
6.4    QUICK-CONNECT/DISCONNECT CARGO COUPLERS (QCDC)    错误!未定义书签。
6.5    SPOOL PIECES    错误!未定义书签。
6.6    POWERED EMERGENCY RELEASE COUPLINGS (PERC)    错误!未定义书签。
6.7    ACCESSORIES    错误!未定义书签。
6.8    OPERATING AND CONTROL SYSTEM DESIGN    错误!未定义书签。
6.9    PAINTING, MARKING , PACKING AND PREPARATION FOR SHIPMENT    错误!未定义书签。
7    INSPECTION AND TESTS    错误!未定义书签。
7.1    MATERIALS    错误!未定义书签。
7.2    FABRICATION CONTROLS    错误!未定义书签。
7.3    SHOP TESTS    错误!未定义书签。
7.4    SITE TESTS    错误!未定义书签。
7.5    CERTIFICATION TESTS    错误!未定义书签。
8    CRITERIA    错误!未定义书签。
8.1    LEAKAGE    错误!未定义书签。
8.2    PRESSURE DROP    错误!未定义书签。
8.3    CONSUMPTIONS OF STEAM    错误!未定义书签。
8.4    LOADS ON SHIP CROSSOVER FLANGES    错误!未定义书签。
9    Guarantee    错误!未定义书签。

1 General Description
This specification describes the minimum technical requirements for the design, manufacture, testing, inspection and supply of the Gangway for MARITIME TERMINAL OF MORON PETROCHEMICAL COMPLEX PROJECT. The suppliers scope of work shall include but shall not be limited to design, fabrication, inspection, testing, preparation for shipment, spare parts, special tools and supply of documentation and manuals. The Gangway shall be in full compliance with this specification and international standards.
This specification does not list all the technical requirements and standards. Suppliers should provide the economic, security and high quality products which shall meet the relevant international technology and standards.
Suppliers shall be responsible for the quality of the contract equipment, spare parts and technical performance.
2 Project Overview
2.1 Construction Site:
Moron Petrochemical Complex, Moron, Venezuela
2.2 Project Scale
The gangway will be installed in Berth-2. Berth-2 is designed for chemical tankers from 3,000~35,000DWT.
Marine Dimensions:
Berth 1: 39m wide x 277m long with deck top elevation at 6.0mCD.
Vessel Dimensions:
Table 2-1 Design Vessel for Berth-2(Chemical Tankers)
Unit: m
Vessel(DWT)
LOA
BEAM
Molded D
Laden Draft
Ammonia
(Liquid)
Smallest
Donau 5752DWT
112
13
N/A
5.7
Actual Vessel
Biggest
35,000DWT Tanker(PIANC)
200
32.2
16.3
11.8
Sulfur
(Liquid)
Smallest
Daiichi Tanker
2999DWT
92.5
13.6
N/A
5.5
Actual Vessel
Biggest
35,000DWT Tanker(PIANC)
200
32.2
16.3
11.8
2.3 Site Data
2.3.1 Climate
Maximum temperature recorded      37 °C
Mean temperature                    27 °C
Minimum temperature recorded        15 °C